Nyamenga Mini Hydropower Plant – Burundi

We could win another competitive contract to upgrade the Nyamenga hydropower plant in the neighbouring nation of Burundi, from an existing capacity of 1.4 MW to 2.8 MW with two additional turbine-generator sets.

This plant augmentation was successfully completed and commissioned in June 2009.

Similar Posts

  • |

    Davora Tea Factories

    We again entered in acquiring distress factories from the banks and entered into tea manufacturing, since 2014 and went on acquiring five factories in down south and one in Ratnapura District, with an annual manufacturing capacity of 4000 Tons. This is a fairly big volume of tea, employing nearly 1000 workers and having more than…